HomePakistanIslamabad Expressway Service Road 44% Complete

Islamabad Expressway Service Road 44% CompletePakistan

hammadkhaksar
By hammadkhaksar
2026-11-28
2 min read

Work on the 8.5-km, three-lane dual carriageway between Faizabad and Gulberg is under way on several sections at once, with underpass work finished.

Islamabad Expressway Service Road 44% Complete
Share:

More than 44 per cent of the development work on the Islamabad Expressway Service Road (East) project has been completed, with construction continuing on an 8.5-kilometre, three-lane dual carriageway between Faizabad and Gulberg.

According to the Capital Development Authority (CDA), work is under way simultaneously on different sections of the project so that it can be completed within the stipulated time. Construction activities include excavation, embankment, subgrade and sub-base development along the corridor.

ADاشتہار / AdvertisementGoogle Ad

The authority said all 153 piles and the slab of the underpass under construction had been completed. Work on the retaining walls of ramps A and B is progressing, while construction of eight culverts for bridges and drainage is also nearing completion.

The progress marks a steady advance on the position reported a week earlier, when the CDA said more than 41 per cent of the work had been completed. The pace of work has picked up as construction teams operate at several points along the route at the same time. The route runs from Faizabad to Gulberg Greens in the capital.

Work on the project has advanced steadily through November. On 7 November, the CDA reported that more than 28 per cent of the work had been completed, rising to more than 31 per cent by 12 November and more than 41 per cent by 21 November.

The CDA has also launched an enforcement operation against illegal constructions and encroachments along the service road to remove hurdles to the project. In an earlier phase of the drive, 58 buildings were sealed and 124 structures demolished along the route.

Chairman CDA and Chief Commissioner Islamabad Sohail Ashraf has directed the relevant departments to ensure timely completion of the project while maintaining construction quality.

He said the project would help ease traffic congestion on the Islamabad Expressway and improve commuting facilities for residents of Islamabad and Rawalpindi. It would also reduce travel time and fuel consumption, he added.

The CDA said construction would continue at multiple locations along the project corridor to meet the deadline, with excavation, sub-grade, sub-base and top sub-base works progressing on different sections of the road.